Rebuilding Project

The New White Memorial


View renderings of the hospital.

In August 2001 White Memorial Medical Center embarked on a multi-phase campus construction project that is now in its final phase. A key milestone was the opening of a new 8-story specialty care tower on April 26, 2006. The entire campus project will be completed in 2009.

The demolition of the Main and West Buildings, is underway. The first portion began March 3, with "soft demolition" -- removal of everything inside the building, leaving only the building skeleton. Hard demolition – the demolition of the external walls – began at the end of March. A wrecking ball provided dramatic visuals as demolition continued in May. The demolition is expected to be completed at the end of June. After the site is cleared, the last phase of our campus construction -- building a new lobby concourse, gift shop and chapel – will begin. That construction, and our entire project, is estimated for completion at the end of 2009.

Click here to view images of the demolition.

The project consists of:

  • New Construction
  • Retrofitting/Remodeling
  • Equipment Upgrades

The result will be a new White Memorial that continues to set the standards of excellence for health care in our community.

Project Scope and Timeline

  • Central Utilities Upgrade — Completed 2003
  • White Memorial Medical Plaza II Office Building — Completed 2004
  • New Specialty Care Tower — Opened April 26, 2006
  • Retrofitting and Remodeling — Started May 2006
  • Demolitions — Started January 2008
  • New Lobby, Chapel and Main Entrance Construction — 2008-2009
  • Project completion — Late 2009